Action Date |
Action Description |
Apr 19, 2023 |
Assent Application Received |
Apr 19, 2023 |
CHA Worksheet received |
Apr 24, 2023 |
Administrative Review for Completeness |
Apr 25, 2023 |
Plans Received |
May 04, 2023 |
US Army Corps of Engineers Approval Received |
May 08, 2023 |
Application Accepted |
May 08, 2023 |
Project Manager |
May 08, 2023 |
Eng Team Review for Completeness |
May 08, 2023 |
Bio Team Review for Completeness |
May 19, 2023 |
HPHC Historical Preservation No Effect |
Jun 19, 2023 |
30 day Public Notice Issued |
Jul 19, 2023 |
Public Notice End Date |
Sep 06, 2023 |
Additional Information Requested from Applicant |
Sep 13, 2023 |
Additional Information Received |
Oct 02, 2023 |
Additional Information Requested from Applicant |
Oct 02, 2023 |
Public Hearing Notices Mailed |
Oct 02, 2023 |
Category B assigned |
Oct 04, 2023 |
Correspondence Received |
Oct 11, 2023 |
Phone Call |
Oct 11, 2023 |
Correspondence Mailed/Faxed/E-mailed |
Oct 13, 2023 |
Biologist Report |
Oct 13, 2023 |
Engineering Report |
Oct 17, 2023 |
Note to File |
Oct 17, 2023 |
Correspondence Mailed/Faxed/E-mailed |
Oct 17, 2023 |
Correspondence Received |
Oct 18, 2023 |
Correspondence Received |
Oct 24, 2023 |
Comments Received |
Oct 24, 2023 |
Semi-Monthly Meeting Held |
Oct 24, 2023 |
Continued Application by the Council |
Oct 25, 2023 |
Comments Received |
Oct 26, 2023 |
Comments Received |
Oct 26, 2023 |
Correspondence Received |
Oct 27, 2023 |
Correspondence Received |
Oct 30, 2023 |
Comments Received |
Nov 01, 2023 |
Objections/Comments Received |
Nov 03, 2023 |
Comments Received |
Nov 07, 2023 |
Correspondence Received |
Nov 14, 2023 |
Correspondence Received |
Nov 17, 2023 |
Correspondence Received |
Nov 22, 2023 |
Comments Received |
Nov 24, 2023 |
Comments Received |
Nov 29, 2023 |
Correspondence Received |
Nov 29, 2023 |
Meeting Held |
Dec 04, 2023 |
Correspondence Received |
Feb 05, 2024 |
Correspondence Received |
Feb 07, 2024 |
Additional Information Received |
Feb 21, 2024 |
Phone Call |
Feb 21, 2024 |
Additional Information Requested from Applicant |
Feb 23, 2024 |
30 day Public Notice Issued |
Mar 04, 2024 |
Correspondence Received |
Mar 05, 2024 |
Correspondence Received |
Mar 12, 2024 |
Correspondence Received |
Mar 13, 2024 |
Correspondence Received |
Mar 15, 2024 |
Comments Received |
Mar 25, 2024 |
Objections/Comments Received |
Mar 25, 2024 |
Objections/Comments Received |
Mar 25, 2024 |
Public Notice End Date |
Apr 09, 2024 |
Mail Agenda Notice |
Apr 09, 2024 |
Ready to Schedule Semi-Monthly Meeting |
Apr 16, 2024 |
Meeting Held |
Apr 18, 2024 |
Plans Received |
Apr 19, 2024 |
Letter of Support for Project |
Apr 24, 2024 |
Continued application |
Apr 30, 2024 |
Comments Received |
May 06, 2024 |
Additional Information Received |
May 14, 2024 |
Semi-Monthly Meeting Postponed |
May 17, 2024 |
Additional Information Received |
May 28, 2024 |
Council Approval Granted |
May 28, 2024 |
Semi-Monthly Meeting Date Scheduled |
Jun 26, 2024 |
Stipulation Package from Biologist |
Jun 28, 2024 |
Stipulation Package by Engineer |
Jul 01, 2024 |
Legal Response/Decision |
Jul 01, 2024 |
Typist for Processing |
Jul 01, 2024 |
Permit Approved |
Jul 03, 2024 |
Permit Mailed |
Jul 11, 2024 |
Commencement of Work Notice received |
Jul 11, 2024 |
Correspondence Received |
Oct 02, 2024 |
Land Evidence Date |