Action Date | Action Description |
---|---|
Apr 25, 2023 | Assent Application Received |
Apr 28, 2023 | Administrative Review for Completeness |
Apr 28, 2023 | Bio Team Review for Completeness |
Apr 28, 2023 | Project Manager |
Apr 28, 2023 | Application Accepted |
May 11, 2023 | HPHC Historical Preservation No Effect |
Oct 27, 2023 | Additional Information Received |
Nov 28, 2023 | Biologist Report |
Nov 30, 2023 | Typist for Processing |
Nov 30, 2023 | Executive Sign Off |
Nov 30, 2023 | Sent to Photo Copy |
Nov 30, 2023 | Permit Approved |
Dec 04, 2023 | Permit Mailed |
Jan 17, 2024 | Land Evidence Date |
Aug 16, 2024 | Assent Requirement |