Action Date | Action Description |
---|---|
HPHC Review Pending | |
Apr 28, 2023 | Assent Application Received |
Apr 28, 2023 | CHA Worksheet received |
May 05, 2023 | Bio Team Review for Completeness |
May 05, 2023 | Project Manager |
May 05, 2023 | Application Accepted |
May 05, 2023 | Administrative Review for Completeness |
Jun 05, 2023 | HPHC Historical Preservation No Effect |
Jul 19, 2023 | Biologist Report |
Jul 25, 2023 | Typist for Processing |
Jul 25, 2023 | Executive Sign Off |
Jul 25, 2023 | Sent to Photo Copy |
Jul 25, 2023 | Permit Approved |
Jul 27, 2023 | Permit Mailed |
Oct 11, 2023 | Land Evidence Date |
Oct 23, 2023 | Modification Request |
Oct 25, 2023 | Bio Team Review for Completeness |
Oct 26, 2023 | Administrative Review for Completeness |
Nov 08, 2023 | Biologist Report |
Nov 08, 2023 | Typist for Processing |
Nov 08, 2023 | Executive Sign Off |
Nov 08, 2023 | Sent to Photo Copy |
Nov 08, 2023 | Modification Approved |