Action Date | Action Description |
---|---|
May 31, 2023 | Assent Application Received |
Jun 05, 2023 | Administrative Review for Completeness |
Jun 13, 2023 | Bio Team Review for Completeness |
Jun 13, 2023 | Deficient Application - Owner Notification Sent |
Jun 21, 2023 | Phone Call |
Jul 19, 2023 | Deficiency Response Received |
Jul 21, 2023 | Bio Team Review for Completeness |
Jul 21, 2023 | Application Accepted |
Jul 21, 2023 | Project Manager |
Jul 31, 2023 | HPHC Historical Preservation No Effect |
Sep 29, 2023 | Biologist Report |
Oct 05, 2023 | Typist for Processing |
Oct 05, 2023 | Executive Sign Off |
Oct 05, 2023 | Sent to Photo Copy |
Oct 05, 2023 | Permit Approved |
Oct 06, 2023 | Permit Mailed |
Nov 01, 2023 | Land Evidence Date |