Action Date | Action Description |
---|---|
Engineering Report | |
Awaiting Response from applicant | |
US Army Corps of Engineers Approval Required | |
Jun 08, 2023 | Maintenance Certification Request |
Jun 12, 2023 | Administrative Review for Completeness |
Jun 30, 2023 | Eng Team Review for Completeness |
Jun 30, 2023 | Deficient Application - Owner Notification Sent |
Mar 01, 2024 | Deficiency Response Received |
Mar 01, 2024 | Assent Application Received |
Mar 07, 2024 | Administrative Review for Completeness |
Apr 01, 2024 | Eng Team Review for Completeness |
Apr 01, 2024 | Application Accepted |
Apr 01, 2024 | Project Manager |
Apr 09, 2024 | HPHC Historical Preservation No Effect |
Apr 18, 2024 | Additional Information Requested from Applicant |
Sep 19, 2024 | Additional Information Received |
Oct 11, 2024 | 30 day Public Notice Issued |
Nov 11, 2024 | Public Notice End Date |