Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jun 14, 2023 | Assent Application Received |
Jun 16, 2023 | Administrative Review for Completeness |
Jun 20, 2023 | Bio Team Review for Completeness |
Jun 20, 2023 | Application Accepted |
Jun 20, 2023 | Project Manager |
Jun 23, 2023 | HPHC Historical Preservation No Effect |
Jul 26, 2023 | 30 day Public Notice Issued |
Aug 26, 2023 | Public Notice End Date |
Sep 26, 2023 | Public Notice End Date Extension Granted |
Sep 26, 2023 | Additional Information Received |
Dec 18, 2023 | Plans Received |
Dec 18, 2023 | Additional Information Received |
Dec 21, 2023 | Additional Information Received |
Jan 02, 2024 | Mail Agenda Notice |
Jan 02, 2024 | Biologist Report |
Jan 03, 2024 | Executive Signoff of Staff Reports |
Jan 08, 2024 | Comments Received |
Jan 09, 2024 | Semi-Monthly Meeting Held |
Jan 09, 2024 | Council Approval Granted |
Jan 09, 2024 | Semi-Monthly Meeting Date Scheduled |
Jan 24, 2024 | Stipulation Package from Biologist |
Jan 24, 2024 | Plans Received |
Apr 15, 2024 | Typist for Processing |
Apr 15, 2024 | Executive Sign Off |
Apr 15, 2024 | Sent to Photo Copy |
Apr 15, 2024 | Permit Approved |
Apr 18, 2024 | Permit Mailed |
May 10, 2024 | Land Evidence Date |
Jul 24, 2024 | Commencement of Work Notice received |
Aug 30, 2024 | Assent Requirement |