Action Date | Action Description |
---|---|
Jun 20, 2023 | Freshwater Wetlands Application - New - received |
Jun 22, 2023 | Administrative Review for Completeness |
Jul 12, 2023 | Bio Team Review for Completeness |
Jul 12, 2023 | Application Accepted |
Jul 12, 2023 | Project Manager |
Aug 08, 2023 | HPHC Historical Preservation Comments/Concerns |
Sep 07, 2023 | HPHC Historical Preservation No Effect |
Oct 04, 2023 | Biologist Report |
Oct 05, 2023 | Typist for Processing |
Oct 05, 2023 | Executive Sign Off |
Oct 05, 2023 | Sent to Photo Copy |
Oct 05, 2023 | Permit Approved |
Oct 06, 2023 | Permit Mailed |