Action Date | Action Description |
---|---|
Legal Response/Decision | |
Jun 23, 2023 | Assent Application Received |
Jun 28, 2023 | Administrative Review for Completeness |
Jun 29, 2023 | Eng Team Review for Completeness |
Jun 29, 2023 | Application Accepted |
Jun 29, 2023 | Project Manager |
Jul 11, 2023 | HPHC Historical Preservation No Effect |
Aug 04, 2023 | Additional Information Requested from Applicant |
Oct 02, 2023 | 30 day Public Notice Issued |
Oct 02, 2023 | Plans Received |
Nov 02, 2023 | Public Notice End Date |
Jan 08, 2024 | Plans Received |
Jan 23, 2024 | Public Hearing Notices Mailed |
Jan 31, 2024 | Correspondence Received |
Feb 08, 2024 | Engineering Report |
Feb 27, 2024 | Council Approval Granted |
Feb 27, 2024 | Semi-Monthly Meeting Date Scheduled |
Apr 16, 2024 | Stipulation Package by Engineer |
Apr 16, 2024 | Typist for Processing |
Apr 16, 2024 | Executive Sign Off |
Apr 16, 2024 | Sent to Photo Copy |
Apr 16, 2024 | Permit Approved |
Apr 18, 2024 | Permit Mailed |