Action Date | Action Description |
---|---|
Jun 27, 2023 | Freshwater Wetlands Application - New - received |
Jun 30, 2023 | Administrative Review for Completeness |
Jul 12, 2023 | Bio Team Review for Completeness |
Jul 12, 2023 | Project Manager |
Jul 12, 2023 | Application Accepted |
Aug 01, 2023 | HPHC Historical Preservation No Effect |
Nov 08, 2023 | Biologist Report |
Nov 09, 2023 | Typist for Processing |
Nov 09, 2023 | Executive Sign Off |
Nov 09, 2023 | Sent to Photo Copy |
Nov 09, 2023 | Permit Approved |
Nov 14, 2023 | Permit Mailed |
Oct 04, 2024 | Land Evidence Date |