Action Date | Action Description |
---|---|
Jul 14, 2023 | Maintenance Certification Request |
Jul 18, 2023 | Administrative Review for Completeness |
Jul 19, 2023 | Eng Team Review for Completeness |
Jul 19, 2023 | Application Accepted |
Jul 19, 2023 | Project Manager |
Jul 31, 2023 | HPHC Historical Preservation No Effect |
Aug 22, 2023 | Engineering Report |
Aug 24, 2023 | Typist for Processing |
Aug 24, 2023 | Executive Sign Off |
Aug 24, 2023 | Sent to Photo Copy |
Aug 24, 2023 | Permit Approved |
Aug 25, 2023 | Permit Mailed |
Oct 19, 2023 | Land Evidence Date |