Action Date | Action Description |
---|---|
Jul 20, 2023 | Assent Application Received |
Jul 26, 2023 | Administrative Review for Completeness |
Aug 03, 2023 | Bio Team Review for Completeness |
Aug 03, 2023 | Eng Team Review for Completeness |
Aug 03, 2023 | Application Accepted |
Aug 03, 2023 | Project Manager |
Sep 20, 2023 | Additional Information Received |
Sep 28, 2023 | 15 day Public Notice Issued |
Oct 13, 2023 | Public Notice End Date |
Oct 23, 2023 | Biologist Report |
Oct 23, 2023 | Engineering Report |
Oct 24, 2023 | Typist for Processing |
Oct 24, 2023 | Executive Sign Off |
Oct 24, 2023 | Sent to Photo Copy |
Oct 24, 2023 | Permit Approved |
Oct 26, 2023 | Permit Mailed |
Sep 26, 2024 | Commencement of Work Notice received |
Oct 03, 2024 | Land Evidence Date |