Action Date | Action Description |
---|---|
Jul 21, 2023 | Assent Application Received |
Jul 27, 2023 | Administrative Review for Completeness |
Jul 28, 2023 | Bio Team Review for Completeness |
Jul 28, 2023 | Application Accepted |
Jul 28, 2023 | Project Manager |
Aug 04, 2023 | HPHC Historical Preservation No Effect |
Aug 31, 2023 | Additional Information Requested from Applicant |
Sep 22, 2023 | Correspondence Received |
Sep 22, 2023 | Correspondence Mailed/Faxed/E-mailed |
Nov 14, 2023 | Correspondence Received |
Nov 30, 2023 | Additional Information Received |
Dec 05, 2023 | Additional Information Received |
Jan 30, 2024 | Additional Information Requested from Applicant |
Feb 21, 2024 | Plans Received |
Mar 07, 2024 | Biologist Report |
Mar 08, 2024 | Typist for Processing |
Mar 08, 2024 | Executive Sign Off |
Mar 08, 2024 | Sent to Photo Copy |
Mar 08, 2024 | Permit Approved |
Mar 12, 2024 | Permit Mailed |
Sep 30, 2024 | Land Evidence Date |