Action Date | Action Description |
---|---|
Land Evidence Date | |
Aug 04, 2023 | Maintenance Certification Request |
Aug 08, 2023 | Administrative Review for Completeness |
Aug 24, 2023 | Eng Team Review for Completeness |
Aug 29, 2023 | Deficient Application - Owner Notification Sent |
Sep 07, 2023 | Deficiency Response Received |
Sep 27, 2023 | Eng Team Review for Completeness |
Sep 27, 2023 | Application Accepted |
Sep 27, 2023 | Project Manager |
Oct 12, 2023 | Engineering Report |
Dec 20, 2023 | HPHC Historical Preservation No Effect |
Dec 26, 2023 | Executive Sign Off |
Dec 26, 2023 | Sent to Photo Copy |
Dec 26, 2023 | Permit Approved |
Dec 26, 2023 | Typist for Processing |
Dec 28, 2023 | Permit Mailed |