Action Date | Action Description |
---|---|
Aug 16, 2023 | Maintenance Certification Request |
Aug 22, 2023 | Administrative Review for Completeness |
Sep 01, 2023 | Additional Information Received |
Sep 01, 2023 | Category A assigned |
Sep 08, 2023 | Application Accepted |
Sep 08, 2023 | Bio Team Review for Completeness |
Sep 08, 2023 | Project Manager |
Sep 22, 2023 | HPHC Historical Preservation No Effect |
Oct 19, 2023 | Additional Information Received |
Dec 14, 2023 | Additional Information Received |
Dec 15, 2023 | Typist for Processing |
Dec 15, 2023 | Executive Sign Off |
Dec 15, 2023 | Sent to Photo Copy |
Dec 15, 2023 | Biologist Report |
Dec 15, 2023 | Permit Approved |
Dec 19, 2023 | Permit Mailed |
Jan 05, 2024 | Duplicate Original Assent requested/mailed |
Mar 06, 2024 | Land Evidence Date |
Mar 22, 2024 | Commencement of Work Notice received |
Mar 22, 2024 | Correspondence Received |
Aug 30, 2024 | Assent Requirement |