Action Date | Action Description |
---|---|
Sep 18, 2023 | Assent Application Received |
Sep 22, 2023 | Administrative Review for Completeness |
Oct 06, 2023 | Bio Team Review for Completeness |
Oct 06, 2023 | Application Accepted |
Oct 06, 2023 | Project Manager |
Oct 17, 2023 | HPHC Historical Preservation No Effect |
Feb 05, 2024 | Additional Information Requested from Applicant |
Feb 19, 2024 | Correspondence Received |
Apr 15, 2024 | Plans Received |
Aug 14, 2024 | Biologist Report |
Aug 15, 2024 | Typist for Processing |
Aug 15, 2024 | Executive Sign Off |
Aug 15, 2024 | Sent to Photo Copy |
Aug 15, 2024 | Permit Approved |
Aug 16, 2024 | Permit Mailed |
Aug 22, 2024 | Land Evidence Date |