Action Date | Action Description |
---|---|
Oct 30, 2023 | Assent Application Received |
Nov 03, 2023 | Administrative Review for Completeness |
Nov 07, 2023 | Bio Team Review for Completeness |
Nov 07, 2023 | Application Accepted |
Nov 07, 2023 | Project Manager |
Nov 24, 2023 | HPHC Historical Preservation No Effect |
Dec 18, 2023 | 30 day Public Notice Issued |
Jan 18, 2024 | Public Notice End Date |
Feb 09, 2024 | Dock/1.1.6 Review approval |
Mar 20, 2024 | Biologist Report |
Mar 22, 2024 | Additional Information Received |
Mar 25, 2024 | Typist for Processing |
Mar 25, 2024 | Executive Sign Off |
Mar 25, 2024 | Sent to Photo Copy |
Mar 25, 2024 | Permit Approved |
Apr 02, 2024 | Permit Mailed |
Aug 01, 2024 | Dock Plate re-issue |
Aug 01, 2024 | Land Evidence Date |
Aug 21, 2024 | Commencement of Work Notice received |
Oct 17, 2024 | Dock Post-Construction Certification by Engineer received. |