Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Oct 31, 2023 | Assent Application Received |
Nov 03, 2023 | Administrative Review for Completeness |
Nov 07, 2023 | Bio Team Review for Completeness |
Nov 07, 2023 | Application Accepted |
Nov 07, 2023 | Project Manager |
Nov 24, 2023 | HPHC Historical Preservation No Effect |
Dec 18, 2023 | 30 day Public Notice Issued |
Jan 18, 2024 | Public Notice End Date |
Feb 09, 2024 | Dock/1.1.6 Review approval |
Feb 14, 2024 | Biologist Report |
Feb 16, 2024 | Typist for Processing |
Feb 16, 2024 | Executive Sign Off |
Feb 16, 2024 | Sent to Photo Copy |
Feb 16, 2024 | Permit Approved |
Feb 20, 2024 | Permit Mailed |
Feb 26, 2024 | Land Evidence Date |