Action Date | Action Description |
---|---|
Nov 09, 2023 | Assent Application Received |
Nov 14, 2023 | Administrative Review for Completeness |
Nov 20, 2023 | Bio Team Review for Completeness |
Nov 27, 2023 | Deficient Application - Owner Notification Sent |
Apr 12, 2024 | Deficiency Response Received |
Apr 18, 2024 | Additional Information Received |
Apr 25, 2024 | Bio Team Review for Completeness |
Apr 26, 2024 | Application Accepted |
Apr 26, 2024 | Project Manager |
May 13, 2024 | HPHC Historical Preservation No Effect |
Jun 12, 2024 | Biologist Report |
Jun 18, 2024 | Typist for Processing |
Jun 18, 2024 | Executive Sign Off |
Jun 18, 2024 | Sent to Photo Copy |
Jun 18, 2024 | Permit Approved |
Jun 21, 2024 | Permit Mailed |
Jun 27, 2024 | Land Evidence Date |
Sep 10, 2024 | Commencement of Work Notice received |