Action Date | Action Description |
---|---|
Nov 21, 2023 | Assent Application Received |
Nov 28, 2023 | Administrative Review for Completeness |
Dec 01, 2023 | Bio Team Review for Completeness |
Dec 01, 2023 | Deficient Application - Owner Notification Sent |
Dec 19, 2023 | Deficient Application Picked Up |
Jun 03, 2024 | Deficiency Response Received |
Jun 06, 2024 | Bio Team Review for Completeness |
Jun 06, 2024 | Application Accepted |
Jun 06, 2024 | Project Manager |
Jun 10, 2024 | HPHC Historical Preservation No Effect |
Aug 22, 2024 | Biologist Report |
Aug 27, 2024 | Typist for Processing |
Aug 27, 2024 | Executive Sign Off |
Aug 27, 2024 | Sent to Photo Copy |
Aug 27, 2024 | Permit Approved |
Aug 29, 2024 | Permit Mailed |
Sep 13, 2024 | Land Evidence Date |