Action Date | Action Description |
---|---|
Legal Response/Decision | |
Dock Post-Construction Certification by Engineer received. | |
Nov 28, 2023 | Assent Application Received |
Nov 30, 2023 | Administrative Review for Completeness |
Dec 01, 2023 | Bio Team Review for Completeness |
Dec 01, 2023 | Project Manager |
Dec 01, 2023 | Application Accepted |
Dec 01, 2023 | Category A* (Docks) |
Dec 18, 2023 | 30 day Public Notice Issued |
Dec 20, 2023 | HPHC Historical Preservation No Effect |
Dec 26, 2023 | Objections/Comments Received |
Jan 18, 2024 | Public Notice End Date |
Jan 22, 2024 | Objections/Comments Received |
Feb 18, 2024 | Public Notice End Date Extension Granted |
Feb 19, 2024 | Comments Received |
Feb 20, 2024 | Objections/Comments Received |
Apr 17, 2024 | Additional Information Received |
Apr 25, 2024 | 30 day Public Notice Issued |
May 20, 2024 | Comments Received |
May 24, 2024 | Objections/Comments Received |
May 25, 2024 | Public Notice End Date |
Jun 10, 2024 | Additional Information Received |
Jun 10, 2024 | Semi-Monthly Meeting Date Scheduled |
Jun 10, 2024 | Objection withdrawal received |
Jul 08, 2024 | Mail Agenda Notice |
Jul 09, 2024 | Biologist Report |
Jul 10, 2024 | Supervisor Biologist SignOff |
Jul 10, 2024 | Supervisor Engineer SignOff |
Jul 15, 2024 | Executive Signoff of Staff Reports |
Jul 23, 2024 | Council Approval Granted |
Jul 23, 2024 | Semi-Monthly Meeting Date Scheduled |
Jul 24, 2024 | Stipulation Package from Biologist |
Sep 12, 2024 | Typist for Processing |
Sep 12, 2024 | Executive Sign Off |
Sep 12, 2024 | Permit Approved |
Sep 16, 2024 | Permit Mailed |
Sep 30, 2024 | Land Evidence Date |
Oct 17, 2024 | US Army Corps of Engineers Approval Received |