Action Date | Action Description |
---|---|
Land Evidence Date | |
Dock Post-Construction Certification by Engineer received. | |
Dec 06, 2023 | Assent Application Received |
Dec 07, 2023 | Administrative Review for Completeness |
Apr 08, 2024 | Bio Team Review for Completeness |
Apr 08, 2024 | Application Accepted |
Apr 08, 2024 | Project Manager |
Apr 08, 2024 | Category A* (Docks) |
Apr 08, 2024 | 30 day Public Notice Issued |
Apr 12, 2024 | HPHC Historical Preservation No Effect |
May 08, 2024 | Public Notice End Date |
Jul 10, 2024 | Dock/1.1.6 Review approval |
Sep 11, 2024 | Biologist Report |
Sep 12, 2024 | Typist for Processing |
Sep 12, 2024 | Executive Sign Off |
Sep 12, 2024 | Sent to Photo Copy |
Sep 12, 2024 | Permit Approved |
Sep 16, 2024 | Permit Mailed |