Action Date | Action Description |
---|---|
Land Evidence Date | |
Dec 15, 2023 | Maintenance Certification Request |
Dec 15, 2023 | Assent Application Received |
Dec 20, 2023 | Administrative Review for Completeness |
Dec 29, 2023 | Bio Team Review for Completeness |
Dec 29, 2023 | Application Accepted |
Dec 29, 2023 | Project Manager |
Jan 29, 2024 | Additional Information Requested from Applicant |
Feb 01, 2024 | HPHC Historical Preservation No Effect |
Feb 02, 2024 | Biologist Report |
Feb 09, 2024 | Executive Sign Off |
Feb 09, 2024 | Sent to Photo Copy |
Feb 09, 2024 | Permit Approved |
Feb 09, 2024 | Typist for Processing |
Feb 14, 2024 | Permit Mailed |
Aug 14, 2024 | Land Evidence Date |
Aug 19, 2024 | Modification Request |
Aug 23, 2024 | Administrative Review for Completeness |
Aug 27, 2024 | Additional Information Received |
Aug 28, 2024 | Application Accepted |
Aug 28, 2024 | Bio Team Review for Completeness |
Aug 28, 2024 | Project Manager |
Sep 19, 2024 | HPHC Historical Preservation No Effect |
Oct 11, 2024 | Biologist Report |
Oct 15, 2024 | Typist for Processing |
Oct 15, 2024 | Executive Sign Off |
Oct 15, 2024 | Sent to Photo Copy |
Oct 15, 2024 | Modification Approved |
Oct 17, 2024 | Modification mailed |
Oct 24, 2024 | Commencement of Work Notice received |