Action Date | Action Description |
---|---|
Land Evidence Date | |
Sep 20, 2024 | Assent Application Received |
Sep 24, 2024 | Administrative Review for Completeness |
Sep 25, 2024 | Eng Team Review for Completeness |
Sep 25, 2024 | Bio Team Review for Completeness |
Sep 25, 2024 | Project Manager |
Sep 25, 2024 | Application Accepted |
Oct 01, 2024 | Plans Received |
Oct 16, 2024 | Additional Information Received |
Oct 16, 2024 | HPHC Historical Preservation No Effect |
Oct 17, 2024 | CHA Worksheet received |
Oct 17, 2024 | Additional Information Received |
Oct 18, 2024 | Biologist Report |
Oct 21, 2024 | Typist for Processing |
Oct 21, 2024 | Executive Sign Off |
Oct 21, 2024 | Sent to Photo Copy |
Oct 21, 2024 | Permit Approved |
Oct 24, 2024 | Permit Mailed |