Action Date | Action Description |
---|---|
Aug 16, 2006 | Assent Application Received |
Aug 16, 2006 | Administrative Review for Completeness |
Aug 17, 2006 | Team Review for Completeness |
Aug 17, 2006 | Application Accepted |
Aug 25, 2006 | HPHC Historical Preservation No Effect |
Aug 30, 2006 | Engineering Report |
Aug 30, 2006 | Biologist Report |
Aug 31, 2006 | Typist for Processing |
Aug 31, 2006 | Executive Sign Off |
Aug 31, 2006 | Sent to Photo Copy |
Aug 31, 2006 | Permit Approved |
Sep 18, 2006 | Land Evidence Date |
Jul 16, 2009 | Modification Request |
Jul 17, 2009 | Administrative Review for Completeness |
Jul 20, 2009 | Team Review for Completeness |
Jul 20, 2009 | Team Review for Completeness |
Jul 22, 2009 | Biologist Report |
Jul 22, 2009 | Engineering Report |
Jul 22, 2009 | Typist for Processing |
Jul 22, 2009 | Executive Sign Off |
Jul 22, 2009 | Modification Approved |
Jul 24, 2009 | Sent to Photo Copy |
Aug 06, 2009 | Land Evidence Date |
Aug 27, 2009 | HPHC Historical Preservation No Effect |
May 03, 2010 | Correspondence Mailed/Faxed/E-mailed |