Action Date | Action Description |
---|---|
Sep 01, 2006 | Assent Application Received |
Sep 01, 2006 | Administrative Review for Completeness |
Sep 06, 2006 | Team Review for Completeness |
Sep 06, 2006 | Application Accepted |
Sep 13, 2006 | HPHC Historical Preservation No Effect |
Oct 12, 2006 | Additional Information Requested from Applicant |
Dec 11, 2006 | Additional Information Received |
Dec 27, 2006 | Correspondence Received |
Jan 09, 2007 | Correspondence Received |
Mar 15, 2007 | Correspondence Mailed/Faxed/E-mailed |
May 30, 2007 | Additional Information Received |
Jun 04, 2007 | Additional Information Received |
Jun 15, 2007 | 30 day Public Notice Issued |
Jun 15, 2007 | Plans Received |
Jun 21, 2007 | Plans Received |
Jul 03, 2007 | Correspondence Received |
Jul 15, 2007 | Public Notice End Date |
Jul 19, 2007 | Biologist Report |
Jul 19, 2007 | Engineering Report |
Jul 23, 2007 | Correspondence Received |
Jul 24, 2007 | Semi-Monthly Meeting Held |
Jul 24, 2007 | Council Approval Granted |
Jul 24, 2007 | Special Exception Scheduled for Semi-Monthly |
Aug 23, 2007 | Legal Response/Decision |
Oct 22, 2007 | US Army Corp of Engineers Permit Date |
Oct 25, 2007 | US Army Corps of Engineers Approval Received |
Nov 26, 2007 | Additional Information Received |
Dec 05, 2007 | Additional Information Received |
Dec 14, 2007 | Permit Approved |
Dec 14, 2007 | Stipulation Package from Biologist |
Dec 14, 2007 | Stipulation Package by Engineer |
Jan 09, 2008 | Land Evidence Date |
Mar 01, 2010 | Extension of Permit Request |
Mar 18, 2010 | Enforcement Compliance Inspection Required |
Mar 22, 2010 | Extension Toll letter mailed |
Jul 27, 2011 | Extension Toll letter mailed |