Action Date | Action Description |
---|---|
Sep 25, 2006 | Assent Application Received |
Sep 26, 2006 | Administrative Review for Completeness |
Sep 27, 2006 | Team Review for Completeness |
Sep 27, 2006 | Application Accepted |
Sep 27, 2006 | Category A* (Docks) |
Oct 03, 2006 | Additional Information Received |
Oct 04, 2006 | 30 day Public Notice Issued |
Oct 13, 2006 | HPHC Historical Preservation No Effect |
Nov 04, 2006 | Public Notice End Date |
Nov 27, 2006 | Correspondence Received |
Dec 01, 2006 | Dock Meeting Scheduled (Admin) |
Dec 01, 2006 | Dock sub-committee Approved |
Dec 01, 2006 | Typist for Processing |
Dec 01, 2006 | Executive Sign Off |
Dec 01, 2006 | Sent to Photo Copy |
Dec 01, 2006 | Permit Approved |
Dec 01, 2006 | Biologist Report |
Dec 01, 2006 | Engineering Report |
Dec 06, 2006 | US Army Corp of Engineers Permit Date |
Dec 07, 2006 | US Army Corps of Engineers Approval Received |
Dec 15, 2006 | Land Evidence Date |
Jun 12, 2007 | Commencement of Work Notice received |