Action Date | Action Description |
---|---|
Nov 03, 2006 | Assent Application Received |
Nov 06, 2006 | Administrative Review for Completeness |
Nov 20, 2006 | Team Review for Completeness |
Nov 20, 2006 | Application Accepted |
Nov 21, 2006 | Biologist Report |
Nov 21, 2006 | Engineering Report |
Nov 21, 2006 | Typist for Processing |
Nov 21, 2006 | Executive Sign Off |
Nov 21, 2006 | Sent to Photo Copy |
Nov 21, 2006 | Permit Approved |
Nov 30, 2006 | HPHC Historical Preservation No Effect |
Dec 18, 2006 | Assent Correction Mailed |
Dec 21, 2006 | Land Evidence Date |
Mar 22, 2007 | Land Evidence Date |