Action Date | Action Description |
---|---|
Dec 12, 2006 | Assent Application Received |
Dec 13, 2006 | Administrative Review for Completeness |
Dec 13, 2006 | Team Review for Completeness |
Dec 13, 2006 | Team Review for Completeness |
Dec 13, 2006 | Application Accepted |
Dec 13, 2006 | Category A* (Docks) |
Dec 18, 2006 | 30 day Public Notice Issued |
Jan 18, 2007 | Public Notice End Date |
Feb 14, 2007 | Plans Received |
Feb 15, 2007 | Typist for Processing |
Feb 15, 2007 | Executive Sign Off |
Feb 15, 2007 | Sent to Photo Copy |
Feb 15, 2007 | Biologist Report |
Feb 15, 2007 | Engineering Report |
Feb 15, 2007 | Permit Approved |
Mar 22, 2007 | US Army Corp of Engineers Permit Date |
Mar 26, 2007 | US Army Corps of Engineers Approval Received |
Jul 20, 2007 | Land Evidence Date |