Action Date | Action Description |
---|---|
Dec 14, 2006 | Assent Application Received |
Dec 14, 2006 | Administrative Review for Completeness |
Dec 14, 2006 | Team Review for Completeness |
Dec 14, 2006 | Team Review for Completeness |
Dec 14, 2006 | Application Accepted |
Dec 15, 2006 | Biologist Report |
Dec 15, 2006 | Engineering Report |
Dec 18, 2006 | Typist for Processing |
Dec 18, 2006 | Executive Sign Off |
Dec 18, 2006 | Sent to Photo Copy |
Dec 18, 2006 | Permit Approved |
Dec 19, 2006 | HPHC Historical Preservation No Effect |
Jan 10, 2007 | Land Evidence Date |
Jun 30, 2008 | Correspondence Received |
Jun 30, 2008 | ISDS Approved |