Action Date | Action Description |
---|---|
Dec 22, 2006 | Assent Application Received |
Dec 28, 2006 | Administrative Review for Completeness |
Jan 08, 2007 | Deficient Application - Owner Notification Sent |
Dec 06, 2007 | Additional Information Received |
Dec 18, 2007 | Application Accepted |
Jan 29, 2008 | Engineering Report |
Jan 29, 2008 | Typist for Processing |
Jan 29, 2008 | Executive Sign Off |
Jan 29, 2008 | Sent to Photo Copy |
Jan 29, 2008 | Permit Approved |
Feb 22, 2008 | Land Evidence Date |
Jan 31, 2011 | Extension of Permit Request |
Mar 10, 2011 | Extension Toll letter mailed |
Jul 13, 2012 | Extension Toll letter mailed |
Jul 25, 2012 | Correspondence Received |
Jul 18, 2013 | Modification Request |
Jul 19, 2013 | Administrative Review for Completeness |
Jul 19, 2013 | Team Review for Completeness |
Aug 06, 2013 | HPHC Historical Preservation No Effect |
Aug 27, 2013 | Additional Information Received |
Sep 11, 2013 | Typist for Processing |
Sep 11, 2013 | Modification Approved |
Sep 11, 2013 | Biologist Report |
Sep 12, 2013 | Executive Sign Off |
Sep 12, 2013 | Sent to Photo Copy |
Sep 23, 2013 | Land Evidence Date |