Action Date | Action Description |
---|---|
Jan 10, 2007 | Assent Application Received |
Jan 11, 2007 | Administrative Review for Completeness |
Jan 16, 2007 | Team Review for Completeness |
Jan 16, 2007 | Team Review for Completeness |
Jan 16, 2007 | Application Accepted |
Feb 06, 2007 | HPHC Historical Preservation No Effect |
Mar 22, 2007 | Additional Information Received |
Apr 05, 2007 | Biologist Report |
Apr 05, 2007 | Engineering Report |
May 14, 2007 | Supervisor Engineer SignOff |
May 14, 2007 | Supervisor Biologist SignOff |
May 14, 2007 | Executive Sign Off |
Aug 29, 2007 | Mail Agenda Notice |
Aug 29, 2007 | Ready to Schedule Semi-Monthly Meeting |
Sep 05, 2007 | Continuance Requested by Applicant |
Sep 05, 2007 | Continuance request by applicant granted by Director |
Sep 06, 2007 | Mail Agenda Notice |
Sep 11, 2007 | Semi-Monthly Meeting Date Scheduled |
Sep 19, 2007 | Entry of Appearance Received |
Sep 20, 2007 | Continuance Requested by Applicant |
Sep 21, 2007 | Continuance request by applicant granted by Director |
Sep 21, 2007 | Continued Application by the Council |
Sep 24, 2007 | Entry of Appearance Received |
Sep 25, 2007 | Semi-Monthly Meeting Date Scheduled |
Nov 20, 2007 | Additional Information Received |
Dec 13, 2007 | Biologist Report |
Dec 13, 2007 | Engineering Report |
Dec 13, 2007 | Plans Received |
Dec 14, 2007 | Typist for Processing |
Dec 14, 2007 | Permit Approved |
Dec 17, 2007 | Executive Sign Off |
Dec 20, 2007 | Sent to Photo Copy |
Dec 20, 2007 | Chairman's Signoff |
Jan 08, 2008 | Land Evidence Date |
Feb 09, 2010 | Extension of Permit Request |
Mar 17, 2010 | Enforcement Compliance Inspection Required |
Mar 17, 2010 | Process Extension |
Mar 17, 2010 | Extension Toll letter mailed |
May 05, 2015 | Extension of Permit Request |