Action Date | Action Description |
---|---|
Sep 20, 2012 | Assent Application Received |
Sep 21, 2012 | Administrative Review for Completeness |
Sep 25, 2012 | Team Review for Completeness |
Sep 25, 2012 | Deficient Application - Owner Notification Sent |
Nov 15, 2012 | Deficient Application Picked Up |
Dec 05, 2012 | Deficiency Response Received |
Dec 06, 2012 | Team Review for Completeness |
Dec 06, 2012 | Application Accepted |
Dec 26, 2012 | Additional Information Received |
Jan 11, 2013 | HPHC Historical Preservation No Effect |
Jan 11, 2013 | Additional Information Received |
Jan 24, 2013 | 30 day Public Notice Issued |
Feb 14, 2013 | Biologist Report |
Feb 19, 2013 | Category B assigned |
Feb 23, 2013 | Public Notice End Date |
Feb 26, 2013 | Permit Approved |
Feb 27, 2013 | Typist for Processing |
Feb 27, 2013 | Executive Sign Off |
Feb 27, 2013 | Sent to Photo Copy |
Mar 18, 2013 | Land Evidence Date |
Mar 18, 2013 | US Army Corp of Engineers Permit Date |
Apr 25, 2016 | Modification Request |
Apr 25, 2016 | Administrative Review for Completeness |
Apr 27, 2016 | Note to File |
May 02, 2016 | Team Review for Completeness |
May 06, 2016 | HPHC Historical Preservation No Effect |
May 17, 2016 | Biologist Report |
May 18, 2016 | Typist for Processing |
May 27, 2016 | Executive Sign Off |
May 27, 2016 | Sent to Photo Copy |
May 27, 2016 | Modification Approved |
Jul 05, 2016 | Land Evidence Date |