Action Date | Action Description |
---|---|
Oct 30, 2018 | Assent Application Received |
Oct 30, 2018 | Administrative Review for Completeness |
Nov 02, 2018 | Team Review for Completeness |
Nov 02, 2018 | Application Accepted |
Nov 19, 2018 | 30 day Public Notice Issued |
Nov 27, 2018 | HPHC Historical Preservation No Effect |
Dec 19, 2018 | Public Notice End Date |
Feb 11, 2019 | Typist for Processing |
Feb 11, 2019 | Engineering Report |
Aug 07, 2019 | Modification Request |
Aug 07, 2019 | Administrative Review for Completeness |
Aug 19, 2019 | Team Review for Completeness |
Aug 19, 2019 | Application Accepted |
Sep 06, 2019 | HPHC Review Pending |
Sep 06, 2019 | HPHC Historical Preservation No Effect |
Oct 28, 2019 | Modification Approved |
Oct 28, 2019 | Engineering Report |
Oct 28, 2019 | Permit Approved |