Action Date | Action Description |
---|---|
Jan 04, 2019 | Assent Application Received |
Jan 07, 2019 | Administrative Review for Completeness |
Jan 08, 2019 | Team Review for Completeness |
Jan 08, 2019 | Application Accepted |
Jan 24, 2019 | HPHC Review Pending |
Jan 24, 2019 | HPHC Historical Preservation No Effect |
Feb 26, 2019 | Biologist Report |
Feb 27, 2019 | Executive Sign Off |
Feb 27, 2019 | Sent to Photo Copy |
Feb 27, 2019 | Permit Approved |
Feb 27, 2019 | Typist for Processing |
May 06, 2019 | Land Evidence Date |
Nov 05, 2019 | Assent Requirement |