Action Date | Action Description |
---|---|
Feb 22, 2019 | Assent Application Received |
Feb 22, 2019 | Administrative Review for Completeness |
Mar 25, 2019 | Team Review for Completeness |
Mar 25, 2019 | Application Accepted |
Apr 04, 2019 | HPHC Review Pending |
Apr 04, 2019 | HPHC Historical Preservation No Effect |
Apr 08, 2019 | Typist for Processing |
Apr 08, 2019 | Executive Sign Off |
Apr 08, 2019 | Sent to Photo Copy |
Apr 08, 2019 | Permit Approved |
Apr 08, 2019 | Engineering Report |
Apr 25, 2019 | Land Evidence Date |