Action Date | Action Description |
---|---|
Mar 05, 2019 | Assent Application Received |
Mar 11, 2019 | Administrative Review for Completeness |
Mar 27, 2019 | Team Review for Completeness |
Mar 27, 2019 | Application Accepted |
Apr 22, 2019 | HPHC Review Pending |
Apr 22, 2019 | HPHC Historical Preservation No Effect |
Jun 17, 2019 | Plans Received |
Aug 13, 2019 | Plans Received |
Aug 15, 2019 | Biologist Report |
Aug 16, 2019 | Typist for Processing |
Aug 16, 2019 | Executive Sign Off |
Aug 16, 2019 | Sent to Photo Copy |
Aug 16, 2019 | Permit Approved |
Sep 04, 2019 | Land Evidence Date |
Sep 09, 2019 | Modification Request |
Sep 10, 2019 | Administrative Review for Completeness |
Sep 16, 2019 | Team Review for Completeness |
Sep 18, 2019 | Biologist Report |
Sep 18, 2019 | Typist for Processing |
Sep 18, 2019 | Executive Sign Off |
Sep 18, 2019 | Sent to Photo Copy |
Sep 18, 2019 | Modification Approved |
Sep 27, 2019 | HPHC Historical Preservation No Effect |
Sep 27, 2019 | HPHC Review Pending |
Oct 01, 2019 | Land Evidence Date |