Action Date | Action Description |
---|---|
Assent Requirement | |
Mar 06, 2019 | Assent Application Received |
Mar 11, 2019 | Administrative Review for Completeness |
Mar 21, 2019 | Team Review for Completeness |
Mar 21, 2019 | Application Accepted |
Mar 29, 2019 | HPHC Review Pending |
Mar 29, 2019 | HPHC Historical Preservation No Effect |
Apr 24, 2019 | Biologist Report |
Apr 25, 2019 | Typist for Processing |
Apr 25, 2019 | Executive Sign Off |
Apr 25, 2019 | Sent to Photo Copy |
Apr 25, 2019 | Permit Approved |
May 14, 2019 | Land Evidence Date |
Apr 05, 2021 | Extension of Permit Request |
May 06, 2021 | Enforcement Compliance Inspection Required |
May 13, 2021 | Process Extension |
May 13, 2021 | Extension Approved |
Apr 15, 2024 | Modification Request |
Apr 17, 2024 | Administrative Review for Completeness |
Apr 19, 2024 | Bio Team Review for Completeness |
Apr 19, 2024 | Deficient Application - Owner Notification Sent |
May 06, 2024 | Deficient Application Picked Up |