Action Date | Action Description |
---|---|
Mar 06, 2019 | Assent Application Received |
Mar 11, 2019 | Administrative Review for Completeness |
Mar 15, 2019 | Team Review for Completeness |
Mar 15, 2019 | Application Accepted |
Apr 04, 2019 | HPHC Review Pending |
Apr 04, 2019 | HPHC Historical Preservation No Effect |
May 13, 2019 | Typist for Processing |
May 13, 2019 | Executive Sign Off |
May 13, 2019 | Sent to Photo Copy |
May 13, 2019 | Permit Approved |
May 13, 2019 | Engineering Report |
Aug 02, 2019 | Land Evidence Date |