Action Date | Action Description |
---|---|
Mar 07, 2019 | Assent Application Received |
Mar 11, 2019 | Administrative Review for Completeness |
Mar 11, 2019 | Team Review for Completeness |
Mar 11, 2019 | Application Accepted |
Mar 14, 2019 | Additional Information Received |
Apr 17, 2019 | Additional Information Requested from Applicant |
Apr 22, 2019 | HPHC Historical Preservation No Effect |
Apr 22, 2019 | HPHC Review Pending |
May 08, 2019 | Additional Information Received |
May 10, 2019 | Additional Information Received |
May 14, 2019 | Typist for Processing |
May 14, 2019 | Biologist Report |
May 15, 2019 | Executive Sign Off |
May 15, 2019 | Sent to Photo Copy |
May 15, 2019 | Permit Approved |
Aug 06, 2019 | Land Evidence Date |
Jun 21, 2022 | Correspondence Mailed/Faxed/E-mailed |
Jul 21, 2022 | Assent Requirement |