Action Date | Action Description |
---|---|
Monitoring Report | |
Mar 12, 2019 | Assent Application Received |
Mar 12, 2019 | Administrative Review for Completeness |
Mar 13, 2019 | HPHC Review Pending |
Mar 13, 2019 | Team Review for Completeness |
Mar 13, 2019 | Application Accepted |
Mar 13, 2019 | HPHC Historical Preservation No Effect |
Mar 14, 2019 | 30 day Public Notice Issued |
Apr 09, 2019 | Mail Agenda Notice |
Apr 15, 2019 | Public Notice End Date |
Apr 15, 2019 | Geologist Report |
Apr 23, 2019 | Semi-Monthly Meeting Date Scheduled |
Apr 23, 2019 | Council Approval Granted |
Apr 25, 2019 | Typist for Processing |
Apr 25, 2019 | Permit Approved |
Apr 29, 2019 | Executive Sign Off |
Apr 29, 2019 | Sent to Photo Copy |
May 22, 2019 | Land Evidence Date |
Jan 28, 2020 | Additional Information Received |
Mar 27, 2020 | Monitoring Report |
Feb 22, 2023 | Correspondence Received |