Action Date | Action Description |
---|---|
Apr 16, 2019 | Assent Application Received |
Apr 16, 2019 | Administrative Review for Completeness |
Apr 17, 2019 | Plans Received |
Apr 30, 2019 | Application Accepted |
Apr 30, 2019 | Team Review for Completeness |
May 21, 2019 | HPHC Review Pending |
May 21, 2019 | HPHC Historical Preservation No Effect |
Jun 07, 2019 | Biologist Report |
Jun 10, 2019 | Typist for Processing |
Jun 10, 2019 | Executive Sign Off |
Jun 10, 2019 | Sent to Photo Copy |
Jun 10, 2019 | Permit Approved |
Jun 19, 2019 | Land Evidence Date |
Jan 09, 2020 | Modification Request |
Jan 09, 2020 | Administrative Review for Completeness |
Jan 16, 2020 | Bio Team Review for Completeness |
Jan 16, 2020 | Application Accepted |
Jan 28, 2020 | HPHC Review Pending |
Jan 28, 2020 | HPHC Historical Preservation No Effect |
Mar 25, 2020 | Modification Approved |
Mar 25, 2020 | Permit Approved |
Mar 25, 2020 | Biologist Report |
Mar 25, 2020 | Typist for Processing |
Mar 25, 2020 | Executive Sign Off |
Mar 25, 2020 | Sent to Photo Copy |
Jun 12, 2020 | Land Evidence Date |