Action Date Action Description
Jan 30, 2023 Assent Application Received
Feb 01, 2023 Administrative Review for Completeness
Mar 30, 2023 Bio Team Review for Completeness
Mar 30, 2023 Project Manager
Mar 30, 2023 Application Accepted
Jun 21, 2023 30 day Public Notice Issued
Jul 21, 2023 Public Notice End Date
Aug 01, 2023 Dock/1.1.6 Review approval
Oct 26, 2023 Biologist Report
Nov 07, 2023 Typist for Processing
Nov 07, 2023 Executive Sign Off
Nov 07, 2023 Sent to Photo Copy
Nov 07, 2023 HPHC Historical Preservation No Effect
Nov 07, 2023 Permit Approved
Nov 10, 2023 Permit Mailed
Oct 17, 2024 Dock Post-Construction Certification by Engineer received.

Details:

File No
2023-02-002
Town
Cranston
First Name
Timothy & Emily
Last Name
Spurrell
Street
Seaview Avenue
Location
10 Seaview Avenue
Plat/Map
1
Lot/Block
138
Decision Date
Nov 07, 2023
Dock Reg.No
2535
Project
c/m a 4'x130' residential pier
Description
Docks, Piers, Floats (Residential)
Water Area
Providence River
Easement
0
Acceptance Date
Mar 30, 2023