Action Date | Action Description |
---|---|
Jan 30, 2023 | Assent Application Received |
Feb 01, 2023 | Administrative Review for Completeness |
Mar 30, 2023 | Bio Team Review for Completeness |
Mar 30, 2023 | Project Manager |
Mar 30, 2023 | Application Accepted |
Jun 21, 2023 | 30 day Public Notice Issued |
Jul 21, 2023 | Public Notice End Date |
Aug 01, 2023 | Dock/1.1.6 Review approval |
Oct 26, 2023 | Biologist Report |
Nov 07, 2023 | Typist for Processing |
Nov 07, 2023 | Executive Sign Off |
Nov 07, 2023 | Sent to Photo Copy |
Nov 07, 2023 | HPHC Historical Preservation No Effect |
Nov 07, 2023 | Permit Approved |
Nov 10, 2023 | Permit Mailed |
Oct 17, 2024 | Dock Post-Construction Certification by Engineer received. |