Action Date | Action Description |
---|---|
Jan 31, 2023 | Maintenance Certification Request |
Feb 03, 2023 | Administrative Review for Completeness |
Feb 03, 2023 | Bio Team Review for Completeness |
Feb 10, 2023 | Assent Application Received |
Mar 01, 2023 | Application Accepted |
Mar 01, 2023 | Project Manager |
Mar 09, 2023 | Biologist Report |
Mar 24, 2023 | HPHC Historical Preservation No Effect |
Apr 11, 2023 | Executive Sign Off |
Apr 11, 2023 | Sent to Photo Copy |
Apr 11, 2023 | Typist for Processing |
Apr 13, 2023 | Permit Approved |
Apr 13, 2023 | Permit Mailed |
Oct 02, 2023 | Land Evidence Date |