Action Date | Action Description |
---|---|
Feb 10, 2023 | CHA Worksheet received |
Feb 10, 2023 | Assent Application Received |
Feb 17, 2023 | Administrative Review for Completeness |
Feb 20, 2023 | Bio Team Review for Completeness |
Feb 20, 2023 | Project Manager |
Feb 20, 2023 | Application Accepted |
Mar 24, 2023 | HPHC Historical Preservation No Effect |
May 15, 2023 | Additional Information Received |
May 16, 2023 | Biologist Report |
May 22, 2023 | Typist for Processing |
May 22, 2023 | Executive Sign Off |
May 22, 2023 | Sent to Photo Copy |
May 22, 2023 | Permit Approved |
May 25, 2023 | Permit Mailed |
Jun 02, 2023 | Land Evidence Date |
Feb 14, 2024 | Modification Request |
Feb 19, 2024 | Administrative Review for Completeness |
Feb 22, 2024 | Bio Team Review for Completeness |
Feb 22, 2024 | Project Manager |
Feb 22, 2024 | Application Accepted |
Feb 22, 2024 | Project Manager |
Mar 08, 2024 | HPHC Historical Preservation No Effect |
Apr 29, 2024 | Additional Information Received |
May 03, 2024 | Biologist Report |
May 06, 2024 | Typist for Processing |
May 06, 2024 | Executive Sign Off |
May 06, 2024 | Sent to Photo Copy |
May 06, 2024 | Modification Approved |
May 13, 2024 | Land Evidence Date |