Action Date | Action Description |
---|---|
Feb 12, 1999 | Application Accepted |
Jul 27, 1999 | Meeting Held |
Aug 18, 1999 | Council Approval Granted |
Sep 09, 1999 | Biologist Report |
Sep 09, 1999 | Engineering Report |
Sep 09, 1999 | Permit Approved |
Sep 09, 1999 | Land Evidence Date |
Dec 09, 2003 | Modification Request |
Dec 09, 2003 | 30 day Public Notice Issued |
Dec 18, 2003 | Historical Preservation Approval Granted |
Jan 30, 2004 | Biologist Report |
Jan 30, 2004 | Engineering Report |
Jan 30, 2004 | Typist for Processing |
Jan 30, 2004 | Dock sub-committee Approved |
Feb 03, 2004 | Modification Approved |
Apr 18, 2005 | Modification Request |
Apr 18, 2005 | Administrative Review for Completeness |
Apr 21, 2005 | Team Review for Completeness |
May 03, 2005 | 30 day Public Notice Issued |
May 03, 2005 | Historical Preservation Approval Granted |
May 09, 2005 | HPHC Review Pending |
Jun 03, 2005 | Public Notice End Date |
Jun 10, 2005 | Typist for Processing |
Jun 10, 2005 | Executive Sign Off |
Jun 10, 2005 | Sent to Photo Copy |
Jun 10, 2005 | Modification Approved |
Jun 10, 2005 | Correspondence Received |
Jun 10, 2005 | Biologist Report |
Jun 10, 2005 | Engineering Report |
Jun 27, 2005 | US Army Corp of Engineers Permit Date |
Jun 28, 2005 | US Army Corps of Engineers Approval Received |
Jul 18, 2005 | Land Evidence Date |
Jul 22, 2005 | Commencement of Work Notice received |