Action Date | Action Description |
---|---|
Dec 16, 2004 | Category A assigned |
Dec 16, 2004 | Application Accepted |
Feb 21, 2005 | Typist for Processing |
Feb 21, 2005 | Executive Sign Off |
Feb 21, 2005 | Sent to Photo Copy |
Feb 22, 2005 | Permit Approved |
Apr 11, 2005 | Land Evidence Date |
May 17, 2005 | Modification Request |
May 17, 2005 | Administrative Review for Completeness |
May 18, 2005 | Team Review for Completeness |
May 24, 2005 | 30 day Public Notice Issued |
Jun 09, 2005 | Historical Preservation Approval Granted |
Jun 15, 2005 | Correspondence Received |
Jun 20, 2005 | US Army Corp of Engineers Permit Date |
Jun 24, 2005 | Public Notice End Date |
Jun 27, 2005 | US Army Corps of Engineers Approval Received |
Jun 27, 2005 | Biologist Report |
Jun 27, 2005 | Engineering Report |
Jul 01, 2005 | Typist for Processing |
Jul 01, 2005 | Executive Sign Off |
Jul 01, 2005 | Sent to Photo Copy |
Jul 01, 2005 | Modification Approved |
Aug 22, 2005 | Land Evidence Date |
Sep 16, 2013 | Dock Plate returned/lost |