Action Date | Action Description |
---|---|
Jan 28, 2005 | Assent Application Received |
Jan 31, 2005 | Administrative Review for Completeness |
Jan 31, 2005 | Team Review for Completeness |
Jan 31, 2005 | Application Accepted |
Jan 31, 2005 | Engineering Report |
Feb 02, 2005 | Typist for Processing |
Feb 02, 2005 | Executive Sign Off |
Feb 02, 2005 | Sent to Photo Copy |
Feb 03, 2005 | Permit Approved |
Feb 14, 2005 | Land Evidence Date |