Action Date |
Action Description |
|
Violation Exists on this Site (NOV) |
|
Monitoring Report |
Jan 28, 2005 |
Assent Application Received |
Jan 31, 2005 |
Administrative Review for Completeness |
Feb 01, 2005 |
Team Review for Completeness |
Feb 01, 2005 |
Application Accepted |
Feb 01, 2005 |
Category B assigned |
Feb 23, 2005 |
Additional Information Received |
Feb 25, 2005 |
30 day Public Notice Issued |
Mar 03, 2005 |
Additional Information Received |
Mar 26, 2005 |
Public Notice End Date |
Mar 31, 2005 |
Correspondence Received |
Apr 01, 2005 |
Correspondence Received |
Apr 08, 2005 |
Executive Sign Off |
Apr 08, 2005 |
Engineering Report |
Apr 08, 2005 |
Biologist Report |
Apr 20, 2005 |
Correspondence Received |
Apr 26, 2005 |
Semi-Monthly Meeting Held |
Apr 26, 2005 |
Council Approval Granted |
Apr 26, 2005 |
Permit Approved |
Apr 29, 2005 |
Stipulation Package from Biologist |
May 02, 2005 |
Typist for Processing |
May 02, 2005 |
Executive Sign Off |
May 03, 2005 |
Sent to Photo Copy |
May 04, 2005 |
Engineering Report |
May 05, 2005 |
Executive Sign Off |
May 05, 2005 |
Land Evidence Date |
May 05, 2005 |
Legal Response/Decision |
Mar 16, 2007 |
Modification Request |
Mar 19, 2007 |
Administrative Review for Completeness |
Mar 20, 2007 |
Team Review for Completeness |
Mar 20, 2007 |
Team Review for Completeness |
Mar 22, 2007 |
Biologist Report |
Mar 22, 2007 |
Engineering Report |
Mar 26, 2007 |
Typist for Processing |
Mar 29, 2007 |
Executive Sign Off |
Mar 29, 2007 |
Sent to Photo Copy |
Mar 29, 2007 |
Modification Approved |
Apr 04, 2007 |
Land Evidence Date |
Aug 31, 2007 |
Modification Request |
Sep 07, 2007 |
Administrative Review for Completeness |
Sep 10, 2007 |
Team Review for Completeness |
Sep 10, 2007 |
Team Review for Completeness |
Sep 21, 2007 |
HPHC Historical Preservation No Effect |
Oct 24, 2007 |
Additional Information Requested from Applicant |
Nov 15, 2007 |
Application Cancelled |
Nov 19, 2007 |
Certified Receipt Received |
Dec 11, 2007 |
Additional Information Received |
Dec 19, 2007 |
Extension of Permit Request |
Dec 19, 2007 |
Correspondence Mailed/Faxed/E-mailed |
Jan 04, 2008 |
Modification Request |
Jan 07, 2008 |
Administrative Review for Completeness |
Jan 07, 2008 |
Team Review for Completeness |
Jan 16, 2008 |
Biologist Report |
Jan 16, 2008 |
Engineering Report |
Jan 16, 2008 |
Typist for Processing |
Jan 16, 2008 |
Executive Sign Off |
Jan 16, 2008 |
Sent to Photo Copy |
Jan 16, 2008 |
Modification Approved |
Feb 04, 2008 |
HPHC Historical Preservation No Effect |
Feb 05, 2008 |
Land Evidence Date |
Mar 10, 2008 |
Correspondence Received |
Mar 18, 2008 |
Correspondence Mailed/Faxed/E-mailed |
Mar 18, 2008 |
Correspondence Mailed/Faxed/E-mailed |
Mar 24, 2008 |
Plans Received |
Mar 24, 2008 |
Enforcement Compliance Inspection Required |
Mar 27, 2008 |
Process Extension |
Mar 27, 2008 |
Interim Approval Granted |
Apr 15, 2008 |
Letter of Authorization |
Jan 28, 2009 |
Extension of Permit Request |
Feb 13, 2009 |
Monitoring Report |
Oct 21, 2009 |
Enforcement Compliance Inspection Required |
Oct 21, 2009 |
Process Extension |
Oct 21, 2009 |
Extension Approved |
Jan 14, 2014 |
Monitoring Report |
Sep 08, 2014 |
Monitoring Report |