Action Date | Action Description |
---|---|
Engineering Report | |
Biologist Report | |
Feb 09, 2005 | Assent Application Received |
Feb 10, 2005 | Administrative Review for Completeness |
Feb 21, 2005 | Team Review for Completeness |
Feb 21, 2005 | Application Accepted |
Nov 08, 2005 | Engineering Report |
Nov 10, 2005 | Typist for Processing |
Nov 10, 2005 | Executive Sign Off |
Nov 10, 2005 | Sent to Photo Copy |
Nov 10, 2005 | Permit Approved |
Jan 26, 2006 | Land Evidence Recording on Hold |
May 23, 2006 | Land Evidence Date |
Sep 17, 2024 | Modification Request |
Sep 19, 2024 | Administrative Review for Completeness |
Sep 23, 2024 | Eng Team Review for Completeness |
Sep 23, 2024 | Bio Team Review for Completeness |
Sep 23, 2024 | Project Manager |
Sep 23, 2024 | Application Accepted |
Sep 23, 2024 | Project Manager |
Oct 10, 2024 | HPHC Historical Preservation No Effect |
Oct 25, 2024 | 30 day Public Notice Issued |
Nov 12, 2024 | US Army Corps of Engineers Project Number received. |
Nov 25, 2024 | Public Notice End Date |