Action Date | Action Description |
---|---|
Apr 29, 2005 | Dredge Application |
May 03, 2005 | Administrative Review for Completeness |
Jun 29, 2005 | Deficient Application - Owner Notification Sent |
Jul 29, 2005 | Deficiency Response Received |
Aug 01, 2005 | Team Review for Completeness |
Aug 01, 2005 | Application Accepted |
Aug 31, 2005 | HPHC Review Pending |
Oct 20, 2005 | Plans Received |
Oct 26, 2005 | US Army Corp of Engineers Permit Date |
Nov 09, 2005 | US Army Corps of Engineers Approval Received |
Nov 28, 2005 | Dredge Report |
Nov 28, 2005 | DEM Dredge Permit |
Nov 29, 2005 | Typist for Processing |
Nov 29, 2005 | Executive Sign Off |
Nov 29, 2005 | Sent to Photo Copy |
Nov 29, 2005 | Permit Approved |
Jan 25, 2006 | Phone Call |
Jan 27, 2006 | Executive Sign Off |
Feb 03, 2006 | Land Evidence Date |